Initial Project Statement
The Area-wide Stormwater Improvement program will provide funding for the repair and upgrade of storm water drainage system capacity deficiencies. The project will include improvements to culverts, channels, detention systems, and other related facilities, and construction of best management practice (BMP) water quality features such as porous pavement applications, storm receptors, and rain gardens in such locations as identified in watershed management plans. This will continue an ongoing SPLOST 2005 project.
Project Updates
Initial SPLOST 2011 Program Project 27 was completed prior to M&C authorizing an additional $2 million being moved into the project from the unused Jail Project Funds. M&C approved a new Project Concept with a listing of 55 Live Stream Replacement Projects. A small portion of those will be completed with the $2,000,000 that M&C moved into the project on August 4, 2020.
Sub-Projects
Project Name | Year Completed | Location/Closest Address |
Midway/Pinecone Place Stormwater Improvement Project | In Progress | Intersection of Midway Rd at Pine Cone Place |
East Creek Bend Stormwater Improvement Project | 2018 | #149 East Creek Bend |
Greencrest Stormwater Improvement Project | 2018 | #475 Greencrest Drive |
Cedar Shoals Bicycle and Stormwater Improvement Project | In Progress | Cedar Shoals Drive (from #1515 to #1735) |
Rockglen/Highland Ave. and Cedar Creek/Lost Tree Trail | In Progress |
|
SPLOST 2011 Project Monthly Update
Key Project Statistics
- Designer: Varies by Sub-Project
- Contractor: Varies by Sub-Project
- Program Manager: Jacobs Engineering
- Sponsor: Transportation and Public Works
- SPLOST 2011 Budget: $2,000,000
- Total Cost: TBD
- Completion Date: Ongoing
*as of 2/17/2022