Project Details
The sub-project includes realigning crosswalks, updating ramps to include truncated domes, replace approximately 120 linear feet of sidewalk, install cross-walk, modify curb and gutter, and install new brick pattern crosswalks.
Safe Routes to School Improvements for the following Schools that have been completed:
- Barnett Shoals Road and Timothy Road Elementary Schools, completed June 2012
- Winterville Elementary School, completed 2013
- Barrow Elementary School improvements, completed April 2014
- Stroud Elementary School, completed August 2016
- Whitehead Road Elementary School, completed August 2016
- J.J. Harris Elementary School, completed August 2016
- Whit Davis Road Elementary School, completed August 2016
- Barnett Shoals Road, completed August 2016
- Oglethorpe Ave. Elementary School, completed August 2016
- Clarke Middle School, completed August 2016
- Alps Road Elementary School, completed August 2016
- H.T. Edwards Campus, completed October 2018
Project Updates
Staff has completed installation of 9 ADA ramps, 210 feet of sidewalk, 210 feet of curb & gutter, and one driveway. The project is anticipated to be completed in May 2019.
Key Project Statistics
- Designer: W R Toole
- Contractor: Georgia Development Partners
- Program Manager: Jacobs Engineering
- Sponsor: Transportation & Public Works
- Original SPLOST Budget: $1,125,369
- Amended Budget: $1,125,369
- Total Cost to date: $1,125,369
- Completion Date: May 2019