Sub-Project 6: Carr's Creek/ Barnett Shoals Road

Project Details

Connector, Project Concept was approved by the M&C on July 5, 2016.  The Preliminary Plans were approved by M&C on January 3, 2017. 

Project Updates

Project schedule for Sub-Project #6 is being delayed due to land acquisition waiting on T&PW and PUD to complete other work on adjacent property before continuing land acquisition task.

Key Project Statistics

  • Designer: To be determined
  • Contractor: To be determined
  • Program Manger: Jacobs Engineering
  • Sponsor: Leisure Services
  • Original SPLOST Budget: $6,000,000
  • Amended Budget: To be determined
  • Total Cost: To be determined
  • Completion Date: To be determined

*as of 10/15/2019