Project Details
Project includes a new pedestrian/bicyclist bridge over the North Oconee River connecting the recently completed greenway segments to the UGA East Campus/River Road area. Current schedule is for the bridge to be substantially complete by fall 2019.
Project Updates
This project was substantially complete as of August 30. Only minor punchlist items remain for construction. Greenway dedication was held on Thursday, September 5th at 5 p.m.
SPLOST 2011 Project Monthly Update
Key Project Statistics
- Designer: Pond and Company
- Contractor: Astra Group, Inc.
- Program Manger: Jacobs Engineering
- Sponsor: Leisure Services
- Original SPLOST Budget: $2,688,207.67
- Grants or other funding: $440,000
- Total Cost to date: $2,688,207.67
- Completion Date: September 2019
*as of 10/15/2019