Sub-Project 5: Bailey Street/Carriage Lane/Barnett Shoals Road Connector

Project Summary

Project concept was approved by the M&C on July 5, 2016.  The Preliminary Plans were approved by M&C on January 3, 2017.  Land acquisition for sub-project 5 has been completed.  Segment 5 construction was approved by M&C at the March 2018 meeting. Sub-Project #5 was completed November 7, 2018. 

Key Project Statistics

  • Designer: W R Toole
  • Contractor: John D. Stephens, Inc.
  • Program Manger: Jacobs Engineering
  • Sponsor: Leisure Services
  • Original SPLOST Budget: $804,023
  • Amended Budget: $804,023
  • Total Cost: $804,023
  • Completion Date: November 2018