Project Summary
Project concept was approved by the M&C on July 5, 2016. The Preliminary Plans were approved by M&C on January 3, 2017. Land acquisition for sub-project 5 has been completed. Segment 5 construction was approved by M&C at the March 2018 meeting. Sub-Project #5 was completed November 7, 2018.
Key Project Statistics
- Designer: W R Toole
- Contractor: John D. Stephens, Inc.
- Program Manger: Jacobs Engineering
- Sponsor: Leisure Services
- Original SPLOST Budget: $804,023
- Amended Budget: $804,023
- Total Cost: $804,023
- Completion Date: November 2018