Project Details
Sub-Project #2 consists of approximately 1.8 miles of multi-use 12’-14’ wide concrete trail with necessary appurtenances.
This section of the Rail to Trails Network extends the Firefly Trail from Old Winterville Road under the existing Athens Bypass to Hancock Road. The project also incorporates a new 200’ flyover bridge to allow future construction of a new GDOT sponsored bypass on ramp.
More details on this project can be found here.
Project Updates
Construction began in the late Summer of 2020 upon final land acquisition and coordination with GDOT. Georgia Development Partners were awarded the construction contract and anticipate final completion in October 2021.
For future updates, visit TSPLOST 2018, Project 6, Sub-Project 2.
Key Project Statistics
- Designer: Benesch
- Contractor: To be funded through TSPLOST 2018, Project 6
- Program Manager: Jacobs Engineering
- Sponsor: Leisure Services
- Original SPLOST Budget: $738,407
- Total Cost: TBD
- Completion Date: Estimated October 2021
*as of 1/6/21