Sub-Project 6: Solar Energy System Rocksprings Park

Project Details

Solar energy system at the Rocksprings Park Community Center. This work was completed with matching funds from a grant.

Project Updates

Project was awarded to Creative Solar USA, Inc.and was completed at the beginning of January 2020. Dedication was held on March 2, 2020.

Key Project Statistics

  • Designer: Creative Solar USA

  • Contractor: Creative Solar USA
  • Program Manager: Jacobs Engineering
  • Sponsor: Central Services
  • Original SPLOST Budget: $100,000
  • Total Cost: $99,000
  • Completion Date: January 2020