Project Statement
Transit Vehicle Expansion & Replacement Project, will purchase up to 16 buses to replace existing vehicles that have reached the end of useful life. The funding may be used to purchase revenue vehicles and/or support vehicles and/or used to match funding for state and/or federal grants to acquire additional transit vehicles, as required.
Project Updates
To date, the Project has supplied Two 40’ Hybrid heavy-duty buses that were put into service in March 2019, two more in February 2020, and two 35’ Hybrid heavy-duty buses in August 2020. All of these buses were paid with 90% matching grant administered by GDOT. Two additional buses were ordered in January 2023. Delivery is anticipated in late 2024.
Key Project Statistics
- Program Manager: Jacobs Engineering
- Sponsor: Leisure Transit
- SPLOST Budget: $3,920,191
- Grants: $4,044,133
- Total Budget: $7,964,324
- Total Cost to Date: $4,493,626
- Completion Date: TBD