Sub-Project 2: Oconee Hill Cemetery Segment

Project Details

Project Concept was approved by the M&C on August 4, 2015.  Preliminary Plans were approved by M&C on September 6, 2016.  This greenway trail generally traverses the Oconee Hill Cemetery property with the northern and southern termini points connecting the existing greenway. The trail is proposed to be 12’ wide concrete trail that is approximately 3,600 linear feet in length (alignment generally follows existing sanitary sewer route along the river) and would connect the trail along the river from Sandy Creek Nature Center to College Station.

Project Updates

Construction is continuing with approximately 2,600 linear feet (or 56%) of the trail completed. Bridge and retaining wall deep foundation piles have been installed allowing the contractor to begin grading the retaining wall area.  Construction completion is scheduled for December 2022. 

Key Project Statistics

  • Designer: TBD
  • Contractor: Astra Group, LLC
  • Program Manager: Jacobs Engineering
  • Original SPLOST Budget: $3,187.900
  • Grants or other funding: $0.00
  • Total Cost: TBD
  • Completion Date: TBD

*as of 3/18/2022