Sub-Project 4: Research Drive Segment

Project Details

Project Concept was approved by the M&C on August 4, 2015.  The Project User Group has initiated review/planning meetings.  Preliminary Plans were approved by M&C on September 6, 2016.  Segment 4.1 was completed November 7, 2018. 

Project Updates

Land for Sub-Projects #4.2 and #4.3 has been acquired.  Because ACCGov now owns all of the adjacent land, staff is investigating some minor design revisions to avoid sensitive areas that were not possible within the previous easement areas. Revised Preliminary Plans were approved by the M&C at the September 7, 2021 voting meeting. Final design is now underway and will proceed to construction bidding as soon as design & permitting is completed.

Key Project Statistics

  • Designer: TBD
  • Contractor: TBD
  • Program Manager: Jacobs Engineering
  • Original SPLOST Budget: $2,460,000
  • Grants or other funding: $0.00
  • Total Cost: TBD
  • Completion Date: TBD

*as of 4/11/2022