2018-2020 Stormwater Utility Fee Review
Overview
Athens-Clarke County Stormwater is working with Stantec Consulting to conduct a comprehensive review of the Stormwater Utility Fee. This review consists of two phases. The first phase, which wrapped up in December 2018, looked at the existing level and extent of stormwater services, as well as a funding strategy for fixing failing stormwater pipes. Over the past two years, the Stormwater Utility Fee has been used to for emergency stormwater pipe repairs. Annual fee revenue is insufficient to continue to address failing pipes, and therefore, a fee increase is being considered.
The second phase examined the rate structure and credit system. Credits allow stormwater customers to reduce their fees through practices that reduce stormwater runoff and/or reduce the cost burden to ACC for implementation of the Stormwater Management Program. This improves the fairness of our fee system.
Public Input
ACC Stormwater hosted several regional open house meetings to provide information about the Stormwater Utility Fee, the review, and to gather feedback from customers about the fee structure and credits. If any additional meetings are scheduled, they will be posted here.
We are also hosting an online comment form for out-of-state customers or those who cannot make it to in-person meetings. You can find the form here.
If you would like a member of the Stormwater Team to come speak with your neighborhood, business, or civic group about stormwater issues or the Utility Fee, please email stormwater@accgov.com.
Open House at the ACC Library on 1/24/19
Open House at J. J. Harris Elem. on 1/29/19
Resources
- Phase I Public Meeting Presentation (August 2018)
- Stormwater Fee Review announcement (July 2018 stormwater bill stuffer)
- Phase I Survey Results
- Phase I Results Memo
- November 13 Mayor & Commission Work Session Presentation (Watch the recording of the Work Session here; presentation starts at 1:23)
- December 4 Mayor & Commission Meeting Agenda Item (Watch the recording of the meeting here; discussion starts at 1:35:30)
- January ACC Water Bill Insert
- January Postcard Mailer (Note: the Winterville Depot meeting date is incorrect on this card. The meeting will be held on Thursday, February 21.)
- April 9 Mayor & Commission Work Session Presentation (Watch the recording of the Work Session here; presentation starts at 2:01)
- Phase II Results Memo
History
- On February 4, 2003, Mayor and Commission (M&C) approved the ACCGOV Stormwater Management Program (SMP) for compliance with the NPDES Phase II Stormwater Permit. The SMP specified the level and scope of service and identified tasks that ACCGOV would undertake over a five‐year period to comply with regulations identified in the Phase II Permit.
- On April 1, 2003, M&C authorized the Manager’s Office to create a citizen/staff Stormwater Advisory Committee (SAC) to assist with the implementation of the SMP. The SAC’s charge was to review the current funding structure for the SMP and to make recommendations as to how the SMP would be funded in the future.
- Between June and August 2003, the SAC worked with staff to review the types of activities the SMP would include, the level of resources necessary to conduct these activities, and the funding options available to the community to fund these activities.
- On November 4, 2003, M&C designated the following sources as the primary methods of funding for the SMP: a. Special Purpose Local Option Sales Tax b. Additional Development Fees, and Page 2 c. Stormwater Enterprise Fund (Stormwater Utility).
- On January 6, 2004, M&C awarded a contract to Earth Tech, Inc. to assist staff and the SAC with developing recommendations for a rate structure for a stormwater utility.
- On December 7, 2004, M&C adopted the stormwater utility ordinance (Chapter 5‐5) describing proposed rate structure, fees, service areas, and credit policies.
- On July 1, 2005, the Stormwater Utility Fee was implemented. M&C reduced the millage rate by 0.6 mills (from 13.40 to 12.80) to reflect the shift of $1.7 million from the General Fund to the new Stormwater Enterprise Fund via the newly imposed fee.
- On March 4, 2013, the Georgia Supreme Court upheld ACCGOV’s Stormwater Utility Fee against a challenge by a ratepayer. The Georgia Supreme Court reaffirmed that the utility fee is not a tax and upheld ACCGOV’s ability to use a lawsuit filed in a local court to collect unpaid fees.
- On March 14, 2017, Transportation and Public Works (T&PW) staff presented an overview of the SMP at a scheduled M&C work session. T&PW staff recommended proceeding with a consultant to assess the stormwater utility’s equity and effectiveness to make recommendations on adjustments to the rate and credit structure.
- On December 5, 2017, M&C awarded the contract for a stormwater funding review to Stantec Consulting Services and Ecological Planning Group.
- In August and September 2018, T&PW advertised an online survey to gather public input on the scope of services provided by the SMP. The survey had 351 responses, as summarized in Attachment #2.
- On August 16, 2018, Stantec and T&PW hosted two public meetings to discuss Phase I of the Stormwater Funding Review: Stormwater Costs and Funding Strategy. Approximately 20 ratepayers showed up. Generally, input was with regards to particular stormwater drainage concerns. All completed surveys were added to the summary, as shown in Attachment #2.
- On September 11, 2018, T&PW staff presented at a scheduled M&C work session the preliminary findings for Phase I of the Stormwater Funding Review: Stormwater Costs and Funding Strategy. M&C requested a second work session to provide additional opportunity to consider alternatives.
- On November 13, 2018, T&PW staff presented at a scheduled M&C work session additional information for Phase I of the Stormwater Funding Review: Stormwater Costs and Funding Strategy.
- On December 4, 2018, M&C voted to accept the funding strategy recommendations as listed in Facts & Issues #9 and #10 in the corresponding agenda item.
- Between January 24, 2019 and February 26, 2019, staff hosted five open house meetings to discuss the Rate Study with citizens.
- On April 9, 2019, T&PW staff presented at a scheduled M&C work session the findings for Phase II of the Stormwater Funding Review.
- On July 2, 2019, M&C unanimously approved the Phase II Technical Memo prepared by Stantec.