Greencrest Drive/East Creek Bend Stormwater Improvements Project

The Greencrest Drive (CE-40) and East Creek Bend Stormwater Improvements Project includes two projects under one construction contract.  

The stormwater improvements for the Greencrest Drive project included grading a drainage swale located within the existing channel behind 115 to 185 Greencrest Drive, and installing new catch basins and approximately 1,350 feet of reinforced concrete pipe (RCP) along Greencrest Drive.  Header curb and roadway milling and overlay was also installed.  


Greencrest Paving 4
Greencrest Paving 5

The East Creek Bend project includes the removal and replacement of the existing 54" corrugated metal pipe with a 14' x 4' precast bottomless arch culvert.  Work also includes the construction of gabion walls, relocation of an existing waterline and minor asphalt work. 

For more information, please contact Engineering Division at (706) 613-3440.

East Creek Bend 1
East Creek Bend - Down Stream View 1