West Broad Street Sidewalk Gap
Funding Source: TSPLOST, GDOT MMSAG
Project Budget: $210,000
Actual Spent: $139,072.96
Funding Source: TSPLOST 2018-12
Project Description: The project includes design and construction of a 5-foot sidewalk gap on the northern side of West Broad Street (from 2310 W. Broad St to 2434 W Broad St). The sidewalk closes an existing sidewalk gap and connects businesses with multiple apartment complexes and transit stops. The project consists of building approximately 1,100 feet of sidewalk, accessibility ramps, and minor intersection improvements at Camellia Drive.
The construction phase is partially funded by the Georgia Department of Transportation (GDOT) through the Multi Model Safety Access Grant. Construction activities are scheduled to began in August 2020 with final completion issued December 31, 2020.