Project Summary
This project was designed to improve the bus stops throughout Athens-Clarke County. Improvements included one or more of the following: installation of signage, pad pavement, benches, covered shelters, landscaping, bicycle racks, route information, and related bus stop improvements. This is a continuation of a SPLOST 2000 program.
Construction and/or improvements have been completed at two hundred and two (202) bus stop locations.
Key Project Statistics
- Designer: W R Toole Engineers
- Contractor: D. A. Edwards
- Sponsor: ACC Transit
- Project Manager: Keith Sanders
- Original SPLOST Budget: $1,978,618
- Grants or other funding: $114,848
- Total Cost: $2,092,580
- Completion Date: December 2012