Basic Facilities / Infrastructure: Transportation
Transportation Components
- Project 16: Bus Stop Improvements (Shelters) (complete)
- Project 17: Athens Multimodal Transportation Center (complete)
- Project 18: Bridge and Guardrail Improvements (complete)
- Project 19: Bicycle Transportation Improvements (complete)
- Project 20: Storm Drainage Improvement Program (complete)
- Project 21: Local Road Resurfacing (complete)
- Project 22: Dirt Road Program (complete)
- Project 23: Local Road Improvement Projects (complete)
- Project 24: Sidewalk and Other Improvements (complete)
- Project 25: Intersection Improvements (complete)
- Project 26: Downtown Infrastructure Improvements (complete)
- Project 27: Neighborhood Traffic Management Program (complete)
Project 16: Bus Stop Improvements
The project upgraded and improved major transit stops along the Athens Transit Bus System routes. The improvements for these transit stops were evaluated for their specific needs. Improvements include:
- Bicycle racks
- Bus pull-off to allow traffic to have a clear lane while the bus is loading and unloading
- Installation of proper signage, a paved pad, benches, and a covered shelter
- Landscaping
- Route information
Budget
- Original SPLOST Budget: $1,167,792
- Budget Amendments: -$167,721
- Adjusted SPLOST Budget: $1,000,071
- Amount Expended: $999,738
Project 17: Athens Multimodal Transportation Center
This project consisted of constructing a new Transit Bus Transfer Center for ACC buses, UGA buses, and intercity buses. It included the addition of shared parking with the Classic Center, a commuter rail platform, a kiss and ride drop-off area, a pedestrian bridge connector, and on-site infrastructure such as access roads and utility upgrades. It also included necessary off-site improvements to East Broad Street and Foundry Street.
Budget
- Original SPLOST Budget: $7,000,000
- Budget Amendments: $957,043
- Adjusted SPLOST Budget: $7,957,043
- Amount Expended: $7,866,477
Project 18: Bridge & Guardrail Improvements
This project rehabilitated, repaired, and performed maintenance of bridges and guardrails throughout Athens-Clarke County.
Budget
- Original SPLOST Budget: $566,669
- Budget Amendments: -$106,374
- Adjusted SPLOST Budget: $460,295
- Amount Expended: $460,295
Project 19: Bicycle Transportation
This project planned, designed, and constructed a comprehensive bicycle route system by utilizing existing roadways and constructing new bicycle-friendly bridges in Athens-Clarke County. It has connected principal attractions with residential areas through a series of on-street, interconnected routes. The new routes allow for safe and efficient travel of bicycles with particular focus on the area within a two-mile radius surrounding the University of Georgia and the downtown area. The project included installing necessary bicycle route signage and the analysis, design, and construction of the river crossings at the Atlanta Highway and College Station Road bridges.
Budget
- Original SPLOST Budget: $1,065,338
- Budget Amendments: -$120,376
- Adjusted SPLOST Budget: $944,962
- Amount Expended: $944,962
Project 20: Storm Drainage Improvement Program
The project made improvements to existing publicly owned storm drainage systems throughout Athens-Clarke County, including the Brooklyn Creek and Lumpkin Street drainage systems.
Budget
- Original SPLOST Budget: $6,800,029
- Budget Amendments: -$2,73,984
- Adjusted SPLOST Budget: $4,326,045
- Amount Expended: $4,326,045
Project 21: Local Road Resurfacing
This project resurfaced and repaired existing public roads throughout Athens-Clarke County.
Budget
- Original Project Budget: $4,533,353
- Budget Amendments: -$562,799
- Adjusted SPLOST Budget: $3,970,554
- Amount Expended: $3,970,554
Project 22: Dirt Road Program
The project paved existing public dirt roads throughout Athens-Clarke County.
Budget
- Original SPLOST Budget: $1,133,338
- Budget Amendments: $110,391
- Adjusted SPLOST Budget: $1,243,799
- Amount Expended: $1,243,541
Project 23: Local Road Improvement Projects
This project advanced the identified road projects in the Athens-Clarke County Commission approved Long-Range Transportation Plan and the Transportation Improvement Program through conceptual design, engineering, right of way acquisition, and construction. Funds were used as a local match to leverage state and federal funds, including county contract funding. This project was a continuation of the SPLOST IV program.
Budget
- Original SPLOST Budget: $4,533,353
- Budget Amendments: -$1,065,069
- Adjusted SPLOST Budget: $3,468,284
- Amount Expended: $3,213,778
Project 24: Sidewalk & Other Improvements
This project designed, constructed, and improved sidewalks, access ramps, pedestrian signals, school zone crossings, and general pedestrian improvements. Specific projects were developed on a yearly basis and prioritized utilizing a ranking system.
Budget
- Original SPLOST Budget: $906,670
- Budget Amendments: -$123,945
- Adjusted SPLOST Budget: $782,725
- Amount Expended: $782,725
Project 25: Intersection Improvements
This project improved intersections that were identified in the ACC Commission approved Long-Range Transportation Plan and the Transportation Improvement Program. All of the intersections were in areas where there were existing safety, operational, and/or congestion concerns. This project is a continuation of the SPLOST IV program.
Budget
- Original SPLOST Budget: $2,266,676
- Budget Amendments: -$15,228
- Adjusted SPLOST Budget: $2,022,369
- Amount Expended: $2,022,369
Locations
- Indian Hills Road left turn lane
- Atlanta Highway / SR Loop 10 connector turn lane
- Whit Davis Road / Old Lexington Road
- Robert Hardman / Morton Road
Project 26: Downtown Infrastructure Improvements
This project constructed, renovated, and repaired various infrastructure and made improvements on the streetscape within the Central Business District. This included remediation of known and suspected utility deficiencies, milling and resurfacing streets, repair and replacement of curbs and sidewalks, and the replacement and installation of new streetscape fixtures, landscaping, and artwork. This project is a continuation of the SPLOST IV program.
Budget
- Original SPLOST Budget: $4,533,353
- Budget Amendments: -$607,087
- Adjusted SPLOST Budget: $3,926,266
- Amount Expended: $3,926,266
Project 27: Neighborhood Traffic Management
This project installed traffic calming devices on local residential streets in Athens-Clarke County. Specific projects were developed jointly with neighborhoods and the Traffic Engineering Division of the Transportation and Public Works Department and presented to the Mayor and Commission for final approval.
Budget
- Original SPLOST Budget: $362,668
- Budget Amendments: -$63,026
- Adjusted SPLOST Budget: $299,642
- Amount Expended: $299,398