Project 57: NA - North Ave./Loop 10 Bridge Replacement Ph1

Executive Summary

Design for replacement of bridges across Loop 10 to allow for bike and pedestrian access across Loop 10 safely.  North Avenue - Extend multi-use trail from Collins Industrial Boulevard to Old Hull Road connecting to the RAISE Grant Improvement. Provide pedestrian connection across Loop 10 along improved bridge.  Approximately 1,800 LF of 10-foot-wide multi-use trail.  Additional coordination with GDOT required. Reconfigure ramps and sidewalks in order to have a safe and efficient overall area.  This project will include preliminary land acquisition and initial construction preparing for the replacement of the bridges.

Project Update - TBD

Estimated Cost:  
TSPLOST 2026 Budget
$7,264,000
Estimated Annual Operating Impact
$7,000

Original Proposed Project Presentation Video