PUD Cross Connection Certificate of Occupancy Resource Documents
PUD Cross Connection Certificate of Occupancy Resource Documents
Last Content Update:
Overview
For the Certificate of Occupancy (C.O.) or the Certificate of Completion (C.O.C.) to be issued, a passing test report for each assembly shall be submitted to the Cross Connection Division prior to requesting Final Inspection.
The Cross Connection coordinator will not be able to off on the final inspection without a passing test report.
Reports can be submitted to backflowsandFOG@acc.com. If an installation was not required, Final Cross Connection installation will require an on-site inspection.
Final inspections are scheduled through Building Inspections.