Clayton Street Improvement Project Update - Oct. 18, 2018

Phase 1 - Pre-Dig - Complete


Crews with the Athens-Clarke County Transportation & Public Works Department completed the Clayton Street Improvement Project Phase 1 - the Pre-Dig - on Wednesday, October 3 after finishing up work on Wall Street.

Thanks to these crews, the work was completed approximately one month ahead of schedule.

Although some private utility relocation work and other non-Clayton Street Improvement construction work will take place between now and 2019, no stormwater or streetscape work will take place related to the Clayton Street Improvements until January 2019 along this corridor.

Clayton Street Improvements - Block 3

Tentative Next Steps


  • October - November - Development of streetscape plans
  • November 20 & December 4 - Tentative Mayor & Commission discussion of streetscape plans (Nov. 20) and vote on plans (Dec. 4)
  • December - Release of documents for private bids on streetscape construction
  • January 2019 - ACC Transportation & Public Works crews begin installation of stormwater infrastructure on Block 1 (N. Lumpkin St. to College Ave.)
  • April 2019 - Contractor begins work on streetscape construction on Block 1 (N. Lumpkin St. to College Ave.)
Clayton Street Improvement Project - Block 1

Clayton Street Improvements Project Timeline 


General tentative project schedule:

  • Pre-Dig Phase (for Stormwater System) - June 18 - Oct. 3, 2018 - Complete
  • Private Utility Relocations - August 2018 - April 2019
  • Stormwater System Installation by Athens-Clarke County - January 2019 - March 2020 (break from August 2019 - January 2020)
  • Streetscape Installation by Private Contractor - April 2019 - August 2020 (break from November 2019 - April 2020)
Clayton Street Improvement Project - Block 2

Pre-Dig for Stormwater System Recap


The Pre-Dig phase for the Clayton Street Improvements started Monday, June 18 when crews started digging trenches for the future stormwater system. Actual installation of the stormwater system will begin in January 2019.

The goal was to discover any issues such as conflicts with other underground items earlier in the process so that the actual installation of the system goes quicker.

Additional information and upcoming dates that relate to the Clayton Street Area project will continue to be sent through this listserve. More information, including detailed maps, are linked at www.accgov.com/clayton.