East Clayton Street Improvements Project Update - April 30, 2021
|
|
|
|
|
Mayor & Commission Approve Streetscape ChangesAt a Special Called Meeting on April 20, 2021, the Mayor and Commission approved several changes to the East Clayton Street Improvements project. They also discussed the changes in length at the April 13, 2021 Work Session. These changes involve planters, sidewalk cafés, road striping, stormwater filtration, overhead lighting, and adding rainbow crosswalks.The changes include: - Eliminating planters except at the corners and the bump-outs;
- Replacing this planter space with concrete sidewalk, widening the space for pedestrians, and adding steps, as needed, from curb to sidewalk, to make up elevation changes;
- Reducing the amount of wide thermoplastic road striping by adding motorcycle parking spots and enlarging bump-outs, without moving stormdrains or losing parking;
- Changing the stormwater filtration system to one installed at East Broad Street and the Firefly Trail instead of using planters for this purpose;
- Changing the festoon overhead lighting layout so that it does not cross over the middle of the streets;
- Revising the layout and amount of the thermoplastic road striping;
- Adding rainbow crosswalks at the College and Clayton intersection.
Each change is explained below. The changes are not expected to impact the general overall schedule for the project, which will run primarily through Spring 2022. Sidewalk CafésThe right-of-way for East Clayton Street varies between buildings from 82 feet to 95 feet in this area. Most buildings are very close to the lot lines, so it is very difficult for the right-of way (street and sidewalk area) to be uniform across the entire project area. The drive lanes are not centered, nor are they parallel to the buildings, making the amount of space available for cafes different between adjacent buildings and between opposite sides of the street. The tightest of spots have less than two feet of space available for sidewalk cafés. As a result of the approved changes and some recent sidewalk café ordinance changes, sidewalk cafés in the smaller areas will be at least 36” wide on East Clayton Street, while also creating larger areas for pedestrian travel. Planters The number of planters in the original plans were partially designed for stormwater purposes (see below) and would have required additional staff to maintain them.
The approved change reduces the number of planters. The reduction means significantly less square footage to maintain. The planters are no longer needed for stormwater purposes due to an alternative approach created that will be more beneficial to downtown.
Additionally, the reduction in planters will provide easier pedestrian access in some narrower areas of the corridor and easier access to vehicles in parking spaces.
The reduced number of planters will not affect the number of trees planted, as the planters were primarily designed for flowers, grasses, and smaller plants. They will have small concrete curbing and fencing similar to the planters on College Square.
Overhead Lighting When the previous plans were approved, the final layout for the festoon or catenary lighting was shown to cross back and forth over East Clayton Street.
Since that time, the International Building Code adopted by Georgia in January 2020 has changed and does not allow the catenary/festoon lighting to cross over the street based on our building conditions.
The overarching concern is safety as emergency response vehicles could potentially become entangled in the wiring and rendered inoperable; thus potentially hampering rescue and fire fighting operations.
Because the plans use low-voltage festoon lighting, there is an option to allow the lighting to be hung from pole to pole, parallel to the sidewalk and trees. This option will still allow additional lighting down the sidewalks until the trees reach a large enough size to allow the lighting to be added to the trees.
|
|
|
|
|
Stormwater System The previous design used the planters as a water quality treatment for stormwater, which would allow for pressure washing the new streetscape area (approximately 3.31 acres).
Staff has designed an alternative approach for water quality treatment unit to remove trash, oil, and sediment near the downstream outfall in conjunction with the existing underground facility located on East Broad Street at the Firefly Trail entrance.
This water quality treatment unit would be an improvement over using the original planters for water quality and does not depend on water going through the soil under Clayton Street for the cleaning. This alternative approach will continue to allow pressure washing.
|
|
|
|
Rainbow Crosswalk
In June 2020, the Mayor and Commission approved the installation of a rainbow crosswalk in support of the LGBTQIA+ community. It was funded as part of TSPLOST 2018 at the June 25, 2020 Mayor and Commission meeting with other pedestrian improvements in the College Avenue and East Broad Street area.
The location at the time was not yet determined. The changes adopted will now place the crosswalks at the College Avenue / East Clayton Street intersection. The crosswalks will be installed once the project is completed and East Clayton Street receives its final repaving and striping, likely by spring 2022.
|
|
|
|
Current Streetscape Tentative Schedule- N. Lumpkin Street to College Avenue - March - August 2021
- College Avenue to Jackson Street - July - October 2021
- Jackson Street to Thomas Street - August 2021 - January 2022
- Jackson Street (Broad Street to Washington Street) - November 2021 - January 2022
- Wall Street - February 2022
Schedule is tentative and subject to change. It is highly dependent on weather and underground factors. More detailed information will be provided in block by block and section by section areas as those areas come closer to construction work.
|
|
|
|
|
Tree Replacements In January 2021, the remaining trees in the area were removed as major construction began in the above ground area.
More trees will be replanted in the area than were removed.
This will occur once the streetscape work is nearly complete. The trees will be planted in better-designed planters with special structural soil. Both are designed for urban landscapes. Planting is expected to take place in late 2021/early 2022.
These trees will include October Glory Red Maples, Avalyn Laurel Oaks, Golden Globe Gingkos, European Hornbeam, Chinese Ironwood, Winter King Hawthorne, and Biloxi Crape Myrtle.
Tree replacement has been a part of the East Clayton Street Improvements Project since the beginning of the project. Many of the former trees were not designed for an urban environment and were not suited for confined spaces. The planters that encase them and the soil used is not as well-designed for this kind of environment as are the currently-designed planters and soil.
New trees better suited to an urban environment will be planted in spaces that are better designed to handle their root systems. These new trees should last for decades, if not longer, without causing the problems of these older ones.
Many of the current trees are also nearing the end of their lifecycle and are not only in decline, but have grown throughout the downtown infrastructure, causing serious issues with sidewalks, utilities, streets, and even buildings.
A similar project removed and replaced the trees on Broad Street and West Clayton Street in the early 2000s, although the streetscape component will be different from those areas.
|
|
|
|
|
Public Restroom Facility Survey Open Through June 15 During the Mayor and Commission Work Session on January 12, 2021, the ACCGov Central Services Department presented options for a public restroom(s) in the downtown area.
Staff recommended the Portland Loo, which is a single public toilet developed for use in urban environments with the preferred location being near the College Avenue parking deck and Washington Street.
Although not specifically part of the East Clayton Street Improvements Project, the facility would have an impact on the area.
As part of the process to consider the public restroom, Central Services has developed a public survey for input about some design options and possible features.
A video of the Work Session presentation and discussion of the proposed public restroom facility is available online on the ACCGov YouTube page at www.youtube.com/accgov or through a direct link to the agenda item discussion.
The survey is available at www.accgov.com/surveys through June 15.
|
|
|
|
|
East Clayton Street Improvements Project Activity Recap / Overview
In May 2020, the Transportation and Public Works Department’s Streets and Drainage Division completed the stormwater infrastructure phase of the project.
In the summer and fall of 2020, private utility companies such as Atlanta Gas Light and Georgia Power relocated and improved their systems in the area. Some additional utility work will take place throughout the project.
In September 2020, installation of a conduit duct bank for street lighting, downtown cameras, traffic and pedestrian signals, and other electrical needs started along the length of the corridor. Once installed on the south side of the street, a second conduit duct bank will be installed on the north side. The conduit duct bank installation is expected to run through October 2021.
In January 2021, streetscape work began on the south side of the first block for sidewalks, curbs, and other ground-level features. A private contractor, Astra Construction, is managing the current and upcoming streetscape phases of the project.
Once completed, the full East Clayton Street Improvements project will enhance East Clayton Street between North Lumpkin Street and North Thomas Street, as well as North Jackson Street between East Broad Street and East Washington Street.
The improvements will include better stormwater management and standing water removal, wider sidewalks with fewer pedestrian conflicts, new streetlights, new traffic signals on fewer poles, public art, wider travel lanes for vehicles, changes to metered spaces’ angles to improve safety when reversing out, larger areas for pedestrians to wait for crossing streets, and more trees and landscaping areas. The Mayor and Commission approved the streetscape design and the public art component in 2019. The majority of the full project is expected to be completed in spring 2022.
|
|
|
|
Additional information and upcoming dates that relate to the Clayton Street Area project will continue to be sent through this listserve.
For more information, including previous newsletters, visit www.accgov.com/clayton.
|
|
|
|
|
|