Project Description This project widened Barnett Shoals from Greencrest Drive to College Station Road from a four-lane road to a five-lane road, installed an extensive storm drainage system, and added sidewalks on both sides. The project is complete.
Budget
- Original SPLOST Budget: $1,200,000
- Budget Amendments: $3,025,903
- Adjusted SPLOST Budget: $4,225,903
- Amount Expended: $4,225,903
|
|