- Home
- Departments
- Departments & Offices A - H
- Athens-Ben Epps Airport
- Pilots
- Airport Construction Update
Airport Construction Update
June 5, 2023
Good evening,
I hope everyone is having a great start to June.
I want to send you all a short progress report on the current projects, along with some information that you need to know related to closures.
- The Runway 2-20 rehabilitation project is moving along nicely. The contractor will complete paving mid-week on runway 2-20 south of 9-27. The contractor will start the north end of the runway this week. Once the north end is completed, we will reopen the portion of Taxiway A that crosses 2-20. This portion has been closed a little longer than expected in order to ensure that the base is strong enough to handle any aircraft weight that is able to taxi to the main runway since this portion of 2-20 is also used as the taxiway to and from the runway 27 end.
- The fencing project is going through final approvals. We hope to get started on the project by August or September.
- We finally received all 3 quotes for the installation of a self-serve unit. Once the purchase order process is completed, we will be able to purchase the unit and work toward installation.
- We continue to move forward on the Taxiway A project. As reported in previous updates, we are redesigning and rebidding the project due to encountering unexpected rock. Since that time we have changed engineering firms and will be changing contractors once the rebidding is completed. Please see the time line below for the current work being done up to bidding. Please remember some of these dates can change depending on the progress being made.
- Schedule Overview
- Survey 06/13/23 – 06/15/23
- Geotech (Rock Borings) (TBD)
- Pre-Design and Validation 06/13/23
- 50% Design Submittal 06/30/23
- 50% Design Review 07/07/23
- 90% Design Submittal 08/11/23
- 90% Design Review 08/18/23
- 100% Design Submittal 08/29/23
- Bid Announcement 08/30/23
- Pre-Bid 09/11/23
- Bid Opening 09/29/23
As you can see, we are very close to getting the Taxiway A project started back up to final completion.
Thank you for your patience as we make our airport better. We have disrupted a lot of asphalt on the airport but it will be worth it when all of the above projects are completed.
Mike
May 25, 2023
Good afternoon all,
We have a lot of moving parts going on at the airport and I wanted to notify you of them.
First off, FAA Flight Check flew the Instrument Landing System and the ILS is operational again. Both the Glideslope and Localizer are working and passed all testing.
The work on runway 2-20 continues. The contractor will begin the final paving on Tuesday of next week.
The contractor should have all of the paving done by June 9th. Once completed, we will then be able to reopen the section of Taxiway Alpha that crosses runway 2-20. The new pavement will need to cure for a short time before they are able to remark the runway.
The airport electrical vault was struck by lightning at some point recently. The transformer that handles the lights for Taxiway A was struck and airport maintenance has ordered the parts to get it back in operation. A NOTAM has been issued that all Taxiway “A” lights are out of service. Please be very careful if you are taxiing in or out of the airport during the nighttime hours. We should have the lights operational again next week once the parts arrive.
The Taxiway “A” project is moving closer to a start date. Our airport engineers continue to work on the redesign of the project. This is still estimated to take 4 months to complete. Then the project will be bid out. I will continue to update you on the progress of the design and bidding of the project and give you a more concrete schedule of when the project will start back as we get closer to bidding.
Be on the lookout for another update next week.
I hope everyone has a great Memorial Day Weekend!
Mike
May 2, 2023
Good afternoon,
May 2023 is already here and I wanted to send out an update on the airport.
- We continue to work toward getting a self-serve unit on the airport. We have received a couple of quotes and are waiting on 1 more in order to move forward with the purchase. I will have a better time line on the installation once all the quotes come in and I know when the unit can be delivered.
- The FAA has completed the work on the VOR and DME and both are back up and usable.
- Flight Check has been called to fly the ILS so that we can get it turned on. I have changed companies that will be maintaining our ILS System. In order to feel comfortable with putting their signature on the maintenance logs, they have been working with the Localizer and Glideslope this week to get it ready for an FAA fight check.
- The Full Depth Reclamation of Runway 2-20 is continuing. The contractor has milled the runway and is installing underdrains. He will then be laying down a concrete and asphalt mixture as a base and then put 4 inches of asphalt on top of that. The project is currently on schedule. The safety areas are being filled in as the added dirt is able to dry and the electricians continue to work on the new lighting for the runway. As you know, both runways are shut down from 8pm-8am until Wednesday morning. They are ahead of schedule and we may be able to open back up sooner. Beginning May 8th, the electricians will be working around the Taxiway A from B to the hold apron. This will force us to close that portion of TWY A from TWY B to the Hold Apron. It will closed continuously for several days. Please check your NOTAMS before you fly to keep up with any closures that may occur during this time.
- The Mayor and Commission approved a fencing project grant from GDOT. This will allow us to install FAA approved perimeter fencing around a portion of the airport. The grant money is a partial amount and the project will be done in two phases. I hope to get this project underway within the next few months.
- The Mayor and Commission approved the redesign and the rebidding of the TWY A project. Our new engineer, RS&H, has done some preliminary design on the project but this approval will give them the authority to finalize the design and move forward on the bidding once the design is completed. The design should take 90 days and the bidding projects will take another 30 days. Once this is completed and a new contractor is on board, we can move the project to completion.
Thank you for your continued support and patience as we work to improve the airport for you and all users of the airport.
Best,
Mike
April 6, 2023
Hello all,
I hope everyone is planning on wonderful weekend!
Just a quick update on the airport.
The Runway 2-20 full depth reclamation project will begin on Monday, 4/10. The runway will be barricaded off until completion. The given time for the project is 75 days from Monday. There will be some work close to the main runway on occasion so please check your NOTAMS on a regular basis or give me, Russ or Davin a quick call or email. We are not planning on closing the main runway for any period of time. We hope that the contractor will work at night when the new runway lights go in and they have to run the line under the runway 9-27. We will definitely keep you all in the loop as that progresses.
We continue to work on the redesign for the Taxiway A project. I am thankful that we are working on that and we hope to open bids in August. GDOT and the FAA continue to work with us on getting this project.
We are currently working on obtaining bids on the new Self-Serve unit. After my last email, I had a chance to go out with a local tenant and show them the potential site. He actually gave me some good advice on a better location just a few feet away but at a better angle. I am excited about this project. It will definitely allow us to provide a less expensive price for this product and will hopefully help your wallets as fuel prices seem to be going up every day.
I am currently working with GDOT to secure some grant money for an FAA approved airport perimeter fence. The airport currently has about 75% of farm fencing with about 25% FAA approved fencing, (10’ high with 3 strands of barb wire). This project will allow us to be 100% fenced in with approved fence and will give us 6-10 feet on both sides for a clear area. The next step is to start the design and environmental then the construction. I am not sure what the time line for this is right now but I am hoping I can get this completed within the next year and a half.
I have secured a contract with a new maintenance technician that will be maintaining our Localizer and Glideslope, along with the MALSF approach lights. The company is AerNav Services and I am excited to have him on board as our FAA approved technician for these airport facilities. He will make sure we are in compliance with all FAA flight checks and that all of our equipment is working properly as it should be. He will be making sue all facilities are up and running once the VOR and DME are fully back on line.
Because of the ever changing conditions on 2-20, Davin or I will start sending out updates on a more regular basis in hopes to keep everyone in the loop with changes that you need to know about.
The UGA Aviation Club will have a Spring Fly-In on April 22th. Come out and support them for a good cause. There will be food and a corn hole tournament to enjoy.
Thank you all for your support.
Mike
March 7, 2023
Good morning all…
After I sent out the last email I had a based customer contact me and ask about our future self-serve unit.
I recently had a meeting with our fuel supplier to see if we could get some financial support from them. They said they would be glad to help us in any way. The airport has some money set aside for this project as well.
I, and Authority Member David Asman, have identified a location that is perfect for the unit. It is on the east side of the airport and has power and phone line already on site. The location will allow for 2-3 planes to pull up for fuel in that area.
I had a self-serve unit at the last airport I managed and it worked very well for us.
The time frame depends on the lead time to get the tank and unit built, shipped and installed. I will add this to my updates as we move forward on this project.
Also, we are looking to put 2 picnic tables, and a very small play area for children, on the eastside of the terminal inside the fenced area. This would give family’s, especially with young children, the opportunity to visit and enjoy the airport while watching the aircraft takeoff and land. Be watching for this in the future.
Thanks,
Mike
February 27, 2023
Good afternoon all:
In an effort to keep you all in the know on what is going on at your airport, I am providing an update below.
1. The FAA continues to work on the VOR. The work will include changing out old cables and antennas and other upgrades. It will also include a frequency change to the VOR which will be NOTAM’d and ultimately published. This work should be completed in March, weather permitting.
Again, just as a reminder, once the VOR work, (DME specifically), is completed, we will set up a flight check on the Localizer and Glide Slope and get them back up again.
2. The Taxiway A project is currently being redesigned and repackaged. This process includes redesign, additional survey and Geotechnical borings and rebidding. The process will take 4 months to complete. Upon completion of this process, we will begin work on the project to completion. Again, the priority will be to get A1-A3 completed FIRST before any other work is done to the east part of Taxiway A. Our main priority will be to get this portion of Taxiway A open again to eliminate having to back taxi on the runway.
3. Runway 2-20 will soon have new asphalt and new lighting. The Runway 2-20 rehabilitation project is slated to begin the first part of April. The project is scheduled to be completed within 60 days of the start date, weather permitting. The project will also include enhanced safety areas at both ends of the runway and perimeter fencing at the approaches.
4. The Runway Obstruction Free Area (ROFA) Project has been completed. The final inspection was conducted last week by the FAA and GDOT and is now closed out as a successful project.
5. AirStar has won the bid on the old “Falcon Hangar”, (Hangar 990). Once the Lease Agreement is signed by the Mayor, they will begin occupancy. We welcome them to the airport and look forward to a long term relationship. Come early Spring, we will begin the Request for Proposal, (RFP), Process on the old “Colvin Hangar”, (Hangar 1080).
6. Lastly, as most of you know, Athens Ben Epps airport is slated to get a new tower in the next few years. Jessica, Tower Chief, and I have been working with the FAA and site consultants to bring this project to the airport. I will update you more on this as progress is made.
I want to thank each one of you for your continued support of the airport.
Please feel free to call or email me with any questions.
Thanks,
Mike
January 25, 2023
Good afternoon all,
I hope you all are having a great start to the new year.
I wanted to send out another airport update in order to keep you better informed on what is going on.
The FAA has started work on the VOR. The work will include changing out old cables and antennas and other upgrades. It will also include a frequency change to the VOR which will be NOTAM’d and ultimately published. This work should be completed in March, weather permitting.
Just a reminder…once the VOR work, (DME specifically), is completed, we will set up a flight check on the Localizer and Glide Slope and get them back up again.
Runway 2-20 will be closed tomorrow and possibly Friday. Contractors will be doing core samples on the runway and the safety areas in preparation for the 2-20 project that will begin in April.
Although there is no noticeable progress, the Taxiway A project continues to move forward. GDOT and the FAA are set to reallocate the funding to a revised project. The intent is to finalize the redesign and begin the rebidding process. As I stated in the past, our first priority is to get A3 completed first and foremost and once we get the rebidding completed, I will have a good timeline that I will share with all of you.
We have two new tenants on the airport. One is a citation that will rent C21 and the other is Airstar who successfully went through the RFP process for the 990 Hangar, (currently the Flight School of Athens). Both will be a welcome addition to the airport.
The airport will soon be sending out another RFP on the Colvin Hangar.
Thank you all for your support of the airport. I thank you for your patience and understanding as we work through some of the issues we have had with Taxiway A. I know this does not make me the most popular person right now but we will get through this and will have something we can be proud of in the end.
Please feel free to call or email me with any questions.
Thanks,
Mike
January 11, 2023
All,
I want to update you on the progress of our projects and the lack of progress on the Taxiway A project and apologize that this email is long overdue.
Taxiway A Project:
As you recall from past updates, the Taxiway A project has experienced several set-backs. These set-backs include a late start by the contractor due COVID restrictions and employee shortages, delays due to waterline and rock issues, supply chain issues, escalation / delay costs, and several months of delay due to the winter shut down. The delay was compounded with all of these issues coming on at one time.
During this time, the airport had to do its due diligence for each one of these concerns in order to make sure that we exhausted all efforts for every obstacle we were facing within this project.
During the life of this project, the airport would move from one issue to another fairly quickly and I did not communicate the progress, or lack of, because we had several balls in the air and plans were changing on a weekly basis as decisions were being made. My intent was not to write a book on the progress, but to communicate with you as the decisions were being finalized along the way.
As noted in the past emails, we are in a stop work mode due to the winter months and some supply chain issues. However, I am now able to firmly say that we are going to be parting ways with the current contractor and we will be repackaging and rebidding this project. This is actually a good thing. The current contractor presented several Change Orders during project that were totally unacceptable to us and we, (along with the FAA and GDOT), decided it was best to cut ties and move on.
Our funding is still intact and we will be able to rebid fairly quickly and get this project started back up again in short order. I will share a time line on this project as soon as we get to that point.
Once we do get started, we will finish up Alpha 3 first thing so we can open it back up before we move on to any other part of the project.
Runway 2-20:
The runway will go through a full depth reclamation project starting in April. The old asphalt will be milled up and then reused with a mix of concrete. Once set, a 4-6 inch layer of asphalt will be placed on top of that. The project also includes new runway lighting. This project does not include any work to be done on TWY B at this time. The project will also enhance the Safety Areas at the end of each runway. This project should only take 45 days to complete, however weather could come into play on some of those days.
Localizer:
The Localizer is operational however it is not usable at this time. The Localizer approach is a LOC/DME approach and relies on the DME. The DME is located at the VOR and is maintained by the FAA. During an FAA Flight Check a few months back, the FAA noticed some irregularities in the signals from the DME. The FAA had since worked on it to fix the issues. However, shortly after that time, the FAA has announced that they plan to do some major work on the VOR. This work will take place from 1/23/2023 until 3/8/2023. The VOR and DME will be unusable during these dates. Once this work is completed, and the DME is up and running again, we will schedule an FAA Fight Check to get the Localizer and Glideslope operational again.
Runway Obstruction Free Area:
The ROFA south of Runway 9-27 and at the approach end of Runway 9 has been cleared. This area was overgrown with small trees and brush and needed to be cleared to satisfy FAA regulations.
The project is completed.
Please feel free to contact me with any questions regarding any of these projects. My direct line is 762-400-7886. Or email me with any questions. Since decisions have been made to a clear path on Taxiway A, I will email you more frequent on the progress of this project. I will also begin regular emails as we get closer to the start of Runway 2-20 project and as we get closer to a Flight Check on the Localizer.
The Athens Ben-Epps Airport is an airport we all can be proud of and this will only enhance the airport for us all.
Thanks,
Mike
September 16, 2022
Good Afternoon,
Please find the airport construction update below.
As most of you know, AHN has received several grants for a multitude of projects that have been on our Capital Improvement Plan. These projects include:
- Localizer Project
- Taxiway A Reconstruction Project
- Runway 2-20 Reconstruction Project, and
- The Runway Obstruction Free Area Clearing
Please see the detailed update below as of this date.
1) The Localizer Project : FAA Flight Check is on the airport today flying the Localizer. They noticed an intermittent signal coming from the DME on the VOR that will have to be looked at by the FAA in order for them to fully deem the Localizer operational. (the Localizer approach relies on the DME). I am thankful that they are being thorough and making sure that all components will be safe. More to come on the Flight Check.
2) The Taxiway A Reconstruction Project
The airport and contractor continue to wait on back ordered materials due to supply chain delays. As mentioned previously, I want them to have all of the supplies in hand once they start work again so the project will not be delayed any further due to other material delays and will continue without interruption until final completion.
Again, I know that the back taxi on 9/27 is not ideal and is a huge inconvenience. Please continue to communicate with each other, especially when the tower is closed for the evening. We will continue to update the NOTAMS as the project progresses and as things change within the scope of the project. In the meantime, we have issued the contractor a Notice-to-Proceed.
This project was designed to put new asphalt and lighting on the Taxiway. The project is split up in two grants. One grant covers the portion of Taxiway A which includes A1, A2 and A3. The other grant includes the work for the new parallel portion past A3 to B3.
3) Runway 2-20 Reconstruction Project: This project will lay new asphalt and new runway lighting. As mentioned previously, this project is currently delayed due to the lack of drainage piping which and electrical components, much like taxiway A. The plan was to get this project started in October, however, the contractor is asking for this project to begin in April. I have agreed to this push due to football season upon us and the fact that we do not want them to start work until the contractor has all materials on site for the project.
4) The Runway Obstruction Free Area Clearing Project: this project is an area of brush and small trees that are in the Safety Area and also the ROFA. Both of these areas must remain clear of any obstructions. This project will not shut down any runways or taxiways but is a must for a safer airport. We are currently working with ACC Purchasing to bid the project out.
I will continue to update you as I get more information.
Please feel free to contact me with any questions you may have about the projects and I will be happy to respond.
Thanks,
Mike
***********************************************************************************************************************************************************
July 26, 2022
Good Afternoon,
Please find the airport construction update below.
As most of you know, AHN has received several grants for a multitude of projects that have been on our Capital Improvement Plan. These projects include:
1) Localizer Project
2) Taxiway A Reconstruction Project
3) Runway 2-20 Reconstruction Project, and
4) The Runway Obstruction Free Area Clearing
Please see the detailed update below as of this date.
1) The Localizer Project : We are currently waiting on the FAA to Flight Check it for sign off. We are told that the FAA is unable to fly the localizer until next month. Once the localizer is approved and turned on, we will then fly the Glide Slope and will once again have all components of the ILS up and running.
2) The Taxiway A Reconstruction Project began 12 months ago and was designed to put new asphalt and lighting on the Taxiway. The project is split up in two grants. One grant covers the portion of Taxiway A which includes A1, A2 and A3. The other grant includes the work for the new parallel portion past A3 to B3.
Last week, the airport met with GDOT, Holt Engineering, and the contractor. The purpose of the meeting was to discuss the project start-up and some of the hurdles that we face such as supply chain delay on cement, drainage pipe, electrical wire, and electrical parts, just to name a few. The airport and contractor are working through those issues and want to make sure that once we get started again, the project is not halted due to additional supply chain delays and that everything will continue on without any further interruption until final completion.
Again, I know that the back taxi on 9/27 is not ideal and is a huge inconvenience. Please continue to communicate with each other, especially when the tower is closed for the evening. We will continue to update the NOTAMS as the project progresses and as things change within the scope of the project.
3) Runway 2-20 Reconstruction Project: This project will lay new asphalt and new runway lighting. As mentioned previously, this project is currently delayed due to the lack of drainage piping which has a 14 week delay. Cement is also an issue and may delay the project even more. We will not start work until the contractor has everything they need for the project.
4) The Runway Obstruction Free Area Clearing Project: this project is an area of brush and small trees that are in the Safety Area and also the ROFA. Both of these areas must remain clear of any obstructions. This project will not shut down any runways or taxiways but is a must for a safer airport. We are currently in the Design Phase of this project.
I will continue to update you as I get more information.
Please feel free to contact me with any questions you may have about the projects and I will be happy respond.
Thanks,
Mike
*****************************************************************************************************************************************************
July 5, 2022
Good Evening,
I hope everyone had a wonderful and safe 4th of July weekend!
As most of you know, AHN has received several grants for a multitude of projects that have been on our Capital Improvement Plan for a while. These projects include:
1) Localizer Project
2) Taxiway A Reconstruction Project
3) Runway 2-20 Reconstruction Project, and
4) The Runway Obstruction Free Area Clearing
Recently, I have been asked by several tenants about the progress of the projects. Because of this, I want to take some time to give you an update on the progress, or in some cases, the lack of progress as it may appear, of all of the projects current and soon to be.
1) The Localizer project began 12 months ago and was designed to relocate the localizer out of the Safety Area and to update the localizer equipment. The Localizer platform has been built and the localizer equipment has been installed. The platform is made of wood and was painted last week. We are currently waiting on the FAA to Flight Check it for sign off. We are told that the FAA is unable to fly the localizer until next month. Once the localizer is approved and turned on, we will then fly the Glide Slope and will once again have all components of the ILS up and running.
2) The Taxiway A Reconstruction project began 12 months ago and was designed to put new asphalt and lighting on the Taxiway. The project is split up in two grants. One grant covers the portion of Taxiway A which includes A1, A2 and A3. The other grant includes the work for the new parallel portion past A3 to B3. The current airport operation allows for A1 and A 2 to be currently used however it does require the aircraft to back taxi from that point. I think we all can agree this is not the ideal situation. There have been several factors that have delayed the project.
A list of the major reasons for the delay is as follows:
a) The project was delayed a little over a month from the start date due to the Construction companies having fewer workers because of the effects of the Pandemic and everyone forced to stay home.
b) The contractor had decided to shut down operations from mid-November until February due to cold weather not being ideal to lay asphalt. The cold temperatures would jeopardize the quality of the final product.
c) Prior to the winter break, the contractor hit several areas of rock in the areas of A3 and the new parallel taxiway area in the project. Time was taken to determine the extent of the rock and what the cost would be to blast the rock down to meet the project design. It was determined that blasting was too expensive and more time was taken to re-design the project to bring the dirt back up to an elevation that would avoid the rock. We are currently working with the contractor on a change order and the project will start up again once everything is approved.
d) The lack of supply is playing into the delay as well. This includes, cement, drainage pipe, electrical wiring and parts for the lighting, not to mention the price of fuel being higher now and much more expensive than it has been just a few months back.
With all of this said, we are working hard to get this project started back and will continue to do so. My goal is to concentrate on getting A1 to A3 completed, including the tie in to the ramp once the project starts back. This will eliminate the back taxi that we are so tired of.
3) Runway 2-20 Reconstruction project will begin in the next few months. This will be coordinated with the UGA football schedule. The project will put down new asphalt and new runway lighting. This project is currently delayed due to the lack of drainage piping which has a 14 week delay. Cement is also an issue and may delay the project even more. We will not start work until the contractor has everything they need for the project.
4) The Runway Obstruction Free Area is the area south of runway 9-27. It is an area of brush and small trees that are in the Safety Area and also the ROFA. Both of these areas must remain clear of any obstructions. This project will not shut down any runways or taxiways but is a must for a safer airport. We are currently in the Design Phase of this project.
I apologize for the long email and explanation, however I thought it was necessary to educate everyone on the projects, old and new. I will continue to update you as I get more information. Future emails won’t be as long since I won’t have to explain the project and will just share updates.
Please feel free to contact me with any questions you may have about the projects and I will be happy respond.
Thanks,
Mike Mathews
Airport Director
706-613-3420 ext. 23